| May 17, 10:42 PM | Daily Report — Superintendent | Jordan Ellis | Site-wide | Submitted | Steel topped out Level 12. Conduit clash open at gridline H7. | frs_0W9X4F2J3M |
| May 17, 6:24 PM | QA Checklist — Concrete Pour | Marcus Rodriguez | Level B2 — south bay | Submitted | Slump 4.5". 4 cylinders cast — 7d, 14d, 28d, hold. | frs_1K4L7B6X2Y |
| May 17, 11:35 AM | Daily Tailgate Briefing | Sam Okafor | Site-wide | Submitted | 142 personnel on site, 4 sub crews. Hot work in Level 04 zone. | frs_2YJ7P6W0L8 |