| RFI-0142 | Door 7B head height conflicts ceiling cloud A-301 Rev B | 08 11 00 | Open | Smith & Assoc. Architecture | 37d late | — |
| RFI-0141 | Slab pour 2L — embed plate EP-12 grid C.5 off design | 03 30 00 | Pending | Carter Structural | 35d late | $18,500.00no schedule hitUSD |
| RFI-0140 | MEP routing above corridor B clashes light cove L3 | 23 31 00 | Responded | Envision GC | 30d late | $4,250.00no schedule hitUSD |
| RFI-0139 | Window sill height discrepancy elevation 3A vs plan | 08 50 00 | OPENCLOSED | — | | — |
| RFI-0138 | Curtain wall anchor CW-7 — confirm embed depth tolerance | 08 44 00 | Open | Skidmore Architects | 53d late | $91,000.00+5d scheduleUSD |
| RFI-0143 | Fireproofing thickness col. C7 — 2hr rating per UL X772 | 07 81 00 | Responded | Envision GC | 25d late | $3,120.00no schedule hitUSD |
| RFI-0144 | Roof drain RD-4 setting — confirm 1/4"/ft slope to overflow | 22 14 23 | Pending | Henderson MEP Engineers | 17d late | — |
| RFI-0145 | Sheet S2.04 — bolt spec for grid line 4 column anchor | 05 50 00 | Open | Carter Structural | 16d late | — |
| RFI-0150 | Foundation pad F-21 — rebar cover < 3" min per ACI 318 | 03 20 00 | Open | Halverson Civil | 50d late | $26,750.00+3d scheduleUSD |
| RFI-0151 | Transformer pad anchor bolt template — verify pattern T2-A | 26 12 19 | Pending | Henderson MEP Engineers | 19d late | $5,400.00no schedule hitUSD |
| RFI-0152 | Switchgear pad expansion joint — sealant compatibility w/ oil | 07 92 00 | Responded | Envision GC | 23d late | $1,840.00no schedule hitUSD |
| RFI-0153 | Grounding grid trench depth — utility requires 30" not 24" | 26 05 26 | Open | Loxsle Development (owner) | 43d late | $42,200.00+4d scheduleUSD |
| RFI-0154 | Yard lighting pole base — drilled-pier vs. spread footing | 26 56 00 | Pending | Halverson Civil | 14d late | $780.00no schedule hitUSD |
| RFI-0155 | Control building slab — verify epoxy floor over post-tension | 09 67 00 | OPENCLOSED | — | | — |
| RFI-0156 | Fire-rated penetration seal at cable tray CT-3 — UL listing | 07 84 00 | Responded | Envision GC | 13d late | $965.00no schedule hitUSD |
| RFI-0157 | Perimeter fence post embedment — frost line revised to 42" | 32 31 13 | VOID | — | | — |