BUILD · WORKFORCE
Workforce
136 on site today · 11 contractors · 17 crews · captured Sun, May 17, 12:00 PM
On site today
136·0vs yesterday
Active contractors
11
Active crews
17
Trades represented
11
Trade rollup
Today's headcount with 7-day trend
| Trade | Today | Δ vs yest. | 7-day trend | Crews | Audit ID |
|---|---|---|---|---|---|
| Concrete | 24 | +2 | 3 | wft_concrete | |
| Electrical | 22 | +2 | 2 | wft_electrical | |
| General / Site | 18 | +1 | 2 | wft_general | |
| Structural Steel | 16 | −2 | 1 | wft_structural_steel | |
| HVAC / Mechanical | 14 | +1 | 2 | wft_mechanical | |
| Drywall / Framing | 12 | −2 | 2 | wft_drywall | |
| Plumbing | 8 | −1 | 1 | wft_plumbing | |
| Carpentry / Finishes | 7 | +1 | 1 | wft_carpentry | |
| Earthwork / Sitework | 6 | −2 | 1 | wft_earthwork | |
| Masonry | 5 | ·0 | 1 | wft_masonry | |
| Roofing / Waterproofing | 4 | ·0 | 1 | wft_roofing |
Contractor crew detail
16 crews| Contractor | Trade | Supervisor | Headcount | Area | Status | Audit ID |
|---|---|---|---|---|---|---|
| Envision Construction GC | General / Site | Jordan Ellis | 18 | Site-wide | Supt. + logistics + safety + QA + GC staff | wfc_meridian_gc |
| Apex Steel Erectors | Structural Steel | Kayla Reeves | 16 | Level 12 — perimeter | Bolt-up at gridline G; topped out yesterday | wfc_apex_steel |
| Olson Concrete & Forming | Concrete | Daniel Olson | 14 | Level B2 — south bay slab | Pouring 4500 PSI mat slab, pour #14 | wfc_olson_concrete_a |
| Voltline Electric | Electrical | Hector Diaz | 14 | Level 04 — MEP rough-in | Pulling conduit feeders to RPP-4A | wfc_volt_electrical_a |
| Aircore Mechanical | HVAC / Mechanical | Wei-Ling Tang | 9 | Roof — AHU pads | Setting AHU-1 isolation pads | wfc_aircore_mech |
| Voltline Electric | Electrical | Robin Carthy | 8 | Switchgear vault — Level B2 | 4000A switchgear staging + LOTO | wfc_volt_electrical_b |
| Hydra Plumbing Co. | Plumbing | Travis Aldridge | 8 | Level 05 — risers | Sanitary risers at zone B | wfc_hydra_plumb |
| Sheetwall Interiors | Drywall / Framing | Priscilla Owens | 8 | Level 07 — drywall hang | Hanging 5/8 type-X at corridors | wfc_sheetwall_drywall_a |
| Meridian Carpentry | Carpentry / Finishes | Owen Briggs | 7 | Lobby — millwork prep | Field-fit walnut casework, lobby reception | wfc_meridian_carp |
| Olson Concrete & Forming | Concrete | Reginald Pierce | 6 | Level 04 — column forms | Stripping forms, prepping column line G | wfc_olson_concrete_b |
| Groundline Excavation | Earthwork / Sitework | Lila Mendoza | 6 | Site — east trench | Trenching for storm lateral SL-3 | wfc_groundline_earth |
| Aircore Mechanical | HVAC / Mechanical | Casey Hwang | 5 | Level 07 — VAV install | Hanging VAVs, branch ductwork | wfc_aircore_mech_b |
| Lithos Masonry | Masonry | Greta Sundholm | 5 | Lobby — limestone veneer | Setting limestone band course at storefront | wfc_lithos_masonry |
| Olson Concrete & Forming | Concrete | Marcus Vaughn | 4 | Level 03 — rebar tying | Tying #8 bars at typical bay layout | wfc_olson_concrete_c |
| Sheetwall Interiors | Drywall / Framing | Theo Brennan | 4 | Level 06 — taping | Level-4 tape + skim at residential corridor | wfc_sheetwall_drywall_b |
| Topshield Roofing | Roofing / Waterproofing | Anwar Khaled | 4 | Roof — north quadrant | Hot-mop application on TPO underlayment | wfc_topshield_roof |