| RFI # | Title | Spec | Status | Ball in court | Due | Cost impact |
|---|---|---|---|---|---|---|
| RFI-0150 | Foundation pad F-21 — rebar cover < 3" min per ACI 318 | 03 20 00 | Open | Halverson Civil | 51d late | $26,750.00+3d scheduleUSD |
| RFI-0154 | Yard lighting pole base — drilled-pier vs. spread footing | 26 56 00 | Pending | Halverson Civil | 15d late | $780.00no schedule hitUSD |