BUILD · MATERIALS

POs, shipments, receipts

4 open POs · 1 in transit · 1 NCRs
OVERSIGHT · MATERIALS

Purchasing & receiving

Across all active project sites.
4open POs$3.5Mcommitted5shipments tracked1in transit1delayed1NCRs open

Purchase orders

PO #VendorDescriptionProjectAmountNeed byStatus
PO-2026-04812Nucor SteelASTM A992 W-shapes — Q3 releaseClinch River BWRX-300$412,4002026-07-15In transit
PO-2026-04839Cemex AggregatesReady-mix concrete — 5,000 PSI · 3,200 CYClinch River BWRX-300$612,5002026-06-15Issued
PO-2026-04857Eaton Power DistributionMain switchgear MV — 3 lineupsClinch River BWRX-300$1,840,0002026-08-30In transit
PO-2026-04898Halliburton CementingSpecialty grout — deep-pour control buildingClinch River BWRX-300$78,2002026-06-04Received
PO-2026-04902Schneider ElectricLow-voltage panelboards — K StreetK Street Garage Pour$184,5002026-06-22Issued
PO-2026-04920Trane Commercial HVACAHUs + RTUs — Helios closeoutHelios Logistics Center$318,4002026-06-10Closed
PO-2026-04948Lincoln ElectricWelding consumables — 30-day refreshClinch River BWRX-300$18,2402026-05-28Draft

Shipments

PO #TrackingCarrierScheduledActualStatus
PO-2026-04812NUC-22481-WMercer Transportation2026-06-04In transit
PO-2026-04857EAT-91202-LOT1Landstar Heavy Haul2026-06-12Scheduled
PO-2026-04857EAT-91202-LOT2Landstar Heavy Haul2026-07-08Scheduled
PO-2026-04898HAL-44012FedEx Freight2026-05-262026-05-25Delivered
PO-2026-04839CEM-DAILY-WK22Cemex Owner Fleet2026-06-01Delayed

Receipts

PO #ReceivedReceived byQty rcvd / ordNCR
PO-2026-048982026-05-25Receiving — Clinch River12 / 12
PO-2026-049202026-05-12Receiving — Helios8 / 8
PO-2026-048392026-05-21Pour Crew A — Clinch River410 / 420NCR