BUILD · FIELD PRODUCTIVITY
Crew output & earned value
6 crews · avg PI 0.93 · CPI 0.96
OVERSIGHT · FIELD PRODUCTIVITY
Crew output & earned value
Weekly crew output reconciled against earned-value cost codes.
6active crews1,800hours / wk0.93avg PI0.96overall CPI1behind2slipping
Crew output — this week
| Crew | Foreman | Trade | Hours / wk | Output / target | PI | Trend |
|---|---|---|---|---|---|---|
| Rebar A | Lloyd Patterson | Rebar / Post-tension | 360 | 84.2 / 90 tons | 0.94 | Slipping |
| Form B | Marcus Kelley | Formwork | 320 | 4,120 / 4,200 SFCA | 0.98 | On track |
| Concrete Pour A | Sam Whitaker | Concrete | 280 | 612 / 600 CY placed | 1.02 | On / over |
| MEP Rough A | Yvonne Castro | MEP | 400 | 1,840 / 2,100 LF conduit | 0.88 | Slipping |
| Steel Erection A | Reggie Tinsley | Structural Steel | 240 | 38 / 40 pcs erected | 0.95 | On track |
| Earthwork A | Devin Marcus | Earthwork | 200 | 18,400 / 22,000 BCY moved | 0.84 | Behind |
Earned progress by cost code
| Cost code | Description | Budget hrs | Actual hrs | Earned hrs | CPI |
|---|---|---|---|---|---|
| 03-30-00 | Cast-in-place concrete | 18,400 | 12,180 | 11,720 | 0.96 |
| 03-21-00 | Reinforcing steel | 6,200 | 4,410 | 4,180 | 0.95 |
| 05-12-00 | Structural steel — fabrication & erection | 8,400 | 5,980 | 6,400 | 1.07 |
| 31-20-00 | Earth-moving & rough grading | 4,800 | 3,240 | 2,720 | 0.84 |
| 26-05-00 | Electrical — power & lighting rough | 12,400 | 6,180 | 5,440 | 0.88 |
| 22-10-00 | Plumbing & process piping | 9,200 | 4,900 | 4,810 | 0.98 |