Subcontracts & purchase orders — SOV, retention, DocuSignProject operating path
Build · Commitments
Subcontracts & purchase orders
Sample mode — DocuSign envelope status from envision-mcp shadow
11active commitments
$60.8MUSD
contract value$14.9MUSD
invoiced to date$1.2MUSD
retention held$152.3KUSD
pending changes2awaiting signature1compliance gaps$837.4KUSD
buyout savings12 commitmentsSorted by contract date · desc
| Number | Title / Vendor | Type | CSI | Exec | Envelope | Revised | Invoiced | Retention | Compliance |
|---|---|---|---|---|---|---|---|---|---|
| SUB-2024-101 | Concrete Pour Package — foundations + cores Smith Concrete Construction · South Harbor Tower | SUB | 03 30 00 | Executed | Executed | Revised$4,342,500.00USD +$142,500 CCO | 60% $2,604,000.00USD | $260,400.00USD 10% withheld | Passing |
| SUB-2024-118 | Structural Steel Erection — Levels 1-22 Stein & Krieg Steel Erectors · South Harbor Tower | SUB | 05 12 00 | Executed | Executed | Revised$10,153,400.00USD +$311,400 CCO | 45% $4,568,530.00USD | $456,853.00USD 10% withheld | Passing |
| PO-2024-318 | Tower Crane Rental — 200-EC-H 18-month Morrow Equipment Company · South Harbor Tower | PO | 01 54 16 | Executed | Executed | Revised$499,400.00USD +$12,400 CCO | 40% $198,760.00USD | $0.00USD | Passing |
| SUB-2024-204 | Curtain Wall — unitised glazing systems Permasteelisa North America · South Harbor Tower | SUB | 08 44 13 | Partial signature | Revised$18,640,000.00USD | 0% $0.00USD | $0.00USD 10% withheld | Expiring | |
| SUB-2025-007 | HVAC — central plant + chilled water distribution Climatec Mechanical · South Harbor Tower | SUB | 23 09 00 | Executed | Executed | Revised$6,304,000.00USD +$184,000 CCO | 30% $1,891,200.00USD | $94,560.00USD 5% withheld | Passing |
| SUB-2025-014 | Electrical — service, distribution, branch Rosendin Electric · South Harbor Tower | SUB | 26 05 00 | Executed | Executed | Revised$8,088,700.00USD +$248,700 CCO | 30% $2,426,610.00USD | $121,330.00USD 5% withheld | Passing |
| PO-2025-082 | Elevator Cab Finishes — 8 high-rise + 2 service Kone North America · South Harbor Tower | PO | 14 21 00 | Partial sig | Partial signature | Revised$1,482,000.00USD | 0% $0.00USD | $0.00USD 5% withheld | Passing |
| SUB-2024-410 | Site Utilities — storm, sanitary, domestic water Atlantic Civil Contractors · Highland Mixed-Use | SUB | 33 30 00 | Executed | Executed | Revised$2,471,400.00USD +$91,400 CCO | 80% $1,976,120.00USD | $197,612.00USD 10% withheld | Expiring |
| SUB-2025-022 | Drywall & Acoustical — residential floors 4-12 Performance Contracting Inc. · Highland Mixed-Use | SUB | 09 29 00 | Executed | Executed | Revised$3,240,000.00USD | 20% $648,000.00USD | $32,400.00USD 5% withheld | Passing |
| PO-2025-118 | PT Cable Material Supply — podium decks VSL Construction Systems · Highland Mixed-Use | PO | 03 23 00 | Executed | Executed | Revised$624,000.00USD | 100% $624,000.00USD | $0.00USD | Passing |
| SUB-2025-031 | Plumbing — domestic + sanitary risers Murray Company Mechanical · Highland Mixed-Use | SUB | 22 10 00 | Sent | Revised$4,980,000.00USD | 0% $0.00USD | $0.00USD 10% withheld | Missing | |
| PO-2024-512 | Site Hoarding & Temporary Fencing — superseded Statewide Fence Co. · Highland Mixed-Use | PO | 01 56 26 | Voided | Voided | Revised$184,000.00USD | 0% $0.00USD | $0.00USD | Blocked |