BUILD · 4D VARIANCE

Captured vs. baseline

8 areas tracked · 4 behind/slipping · 1 tolerance fails
OVERSIGHT · 4D VARIANCE

Captured vs. baseline

LIDAR-anchored captured progress vs. sealed Foresight baseline.
8areas tracked4behind / slipping1tolerance fails+$810Kcost variance-22dworst slip
AreaTradeCaptured % / Planned %Schedule (days)Cost varianceToleranceTrend
Reactor Building — Level 1 deckConcrete (CIP)100% / 100%+2d−$84K4.2mm / ±6mmAhead
Reactor Building — Level 2 wallsConcrete (Tilt)64% / 75%-8d+$218K5.8mm / ±6mmSlipping
Turbine Building — MEP rough-inMEP (Process)28% / 42%-14d+$413K9.1mm / ±12mmBehind
Aux Building — Structural steelSteel91% / 88%+5d−$42K6.8mm / ±4mmAhead
Control Building — Slab on gradeConcrete (SOG)100% / 100%0d$03.9mm / ±6mmOn track
Cooling Tower Foundation — ExcavationEarthwork38% / 60%-22d+$185K18.3mm / ±25mmBehind
Switchyard — FoundationsCivil100% / 100%-3d+$24K7.5mm / ±8mmOn track
Containment Vessel — Liner weldsProcess Piping50% / 55%-4d+$96K1.9mm / ±2mmSlipping