Bid packages
27
19 issued, 8 draft
Envision · Foresight
Project operating path
Delivery method, bid packages by CSI division, prequalification, bid leveling, and award timing.
Bid packages
27
19 issued, 8 draft
Bid leveling
11
active comparisons
Awards
$78.4M
committed trade value
Long-lead risk
4
elevator, switchgear, facade, FFE
Delivery method, bid packages, CSI-division buyout, prequalification, bid leveling, and award timing.
Delivery method
GMP
CM-at-risk basis
Prequal
42 firms
31 cleared
Buyout tracker
63%
long-lead awards next
Is GMP buy-out converging on plan?
Module views
| Subject | Owner | Basis | Status |
|---|---|---|---|
| Elevators | Procurement | 52 wk lead | Award now |
| Concrete | GC | 3 bids leveled | Awarded |
| Facade | Design/GC | VE alternate | Leveling |
South Harbor (SH-2042) · Savannah
Next action: RFI-0142 door head detail