Delta
+$2.8M
vs. feasibility basis
Envision · Foresight
Project operating path
Delta
+$2.8M
vs. feasibility basis
Risk divisions
03 / 07 / 09
high movement
GMP confidence
78%
basis maturity
Burn rate
$420K/wk
preconstruction spend
Live CSI-coded estimate movement, UniFormat crosswalk, burn-rate exposure, and GMP validation.
CSI estimates
97%
coded by division
UniFormat crosswalk
88%
feasibility bridge
GMP validation
78%
scope gaps remain
Will the design land at or below the GMP basis?
Module views
| Subject | Owner | Basis | Status |
|---|---|---|---|
| 07 Envelope | Estimating | +$1.4M | Validate |
| 03 Concrete | Structural | +$820K | Confirmed |
| 12 FFE | Design | -$340K | Accepted |
South Harbor (SH-2042) · Savannah
Next action: RFI-0142 door head detail
GMP confidence
82%
8-quarter trend
Schedule float
12d
vs baseline
Burn rate
$1.4M/wk
8-week
Cost-to-complete
$48M
Trending down
| Code | Bucket | Feasibility | Estimate | Delta $ | Delta % | Status |
|---|---|---|---|---|---|---|
| 03 | Concrete | $12,400,000 | $12,700,000 | +$300,000 | +2.4% | Over |
| 23 | HVAC | $8,900,000 | $9,200,000 | +$300,000 | +3.4% | Over |
| 26 | Electrical | $6,700,000 | $6,900,000 | +$200,000 | +3.0% | Over |
| Total · 3 buckets | $28,000,000 | $28,800,000 | +$800,000 | |||