Cost P80
+$5.6M
above GMP target
Envision · Foresight
Project operating path
Cost P80
+$5.6M
above GMP target
Critical risks
9
3 owner-controlled
Contingency
6.5%
remaining allowance
Schedule float
14d
P50 basis
Risk register, schedule and cost scenarios, allowance exposure, contingency consumption, and P-level outcomes.
Risk register
42
9 critical
Cost scenarios
6
P50/P80/P95
Allowance
$7.2M
unallocated reserve
What's the P-50 / P-90 outcome on schedule and cost?
Module views
| Subject | Owner | Basis | Status |
|---|---|---|---|
| Envelope procurement | Procurement | +23d P80 | Mitigate |
| AHJ inspection cadence | Field | +8d | Monitor |
| FFE lead times | Design | $1.1M risk | Buy early |
South Harbor (SH-2042) · Savannah
Next action: RFI-0142 door head detail