Sample data — connect a live data source (services/rfis).
Build · Field clarifications
RFIs
5open13overdue0due in 3d
Standard CRENew RFI
- 1Submitted
- 2Under Review
- 3Response Drafted
- 4Approved
- 5Closed
| RFI # | Title | Spec | Status | Ball in court | Due | Cost impact |
|---|---|---|---|---|---|---|
| RFI-0142 | Door 7B head height conflicts ceiling cloud A-301 Rev B | 08 11 00 | Open | Smith & Assoc. Architecture | 38d late | — |
| RFI-0138 | Curtain wall anchor CW-7 — confirm embed depth tolerance | 08 44 00 | Open | Skidmore Architects | 54d late | $91,000.00+5d scheduleUSD |
| RFI-0145 | Sheet S2.04 — bolt spec for grid line 4 column anchor | 05 50 00 | Open | Carter Structural | 17d late | — |
| RFI-0150 | Foundation pad F-21 — rebar cover < 3" min per ACI 318 | 03 20 00 | Open | Halverson Civil | 51d late | $26,750.00+3d scheduleUSD |
| RFI-0153 | Grounding grid trench depth — utility requires 30" not 24" | 26 05 26 | Open | Loxsle Development (owner) | 44d late | $42,200.00+4d scheduleUSD |