BUILD · RESOURCE PLANNING

Crews, equipment, workforce

4 active crews · 66 field heads · 4 assets allocated
OVERSIGHT · RESOURCE PLANNING

Allocation across active projects

Crew assignments, equipment allocation, and 30/90-day workforce demand.
4active crews66field headcount4assets allocated0under-utilized3890d net hires

Crew assignments

CrewProjectTradeHeadcountWindowStatus
Rebar AClinch River BWRX-300Rebar / Post-tension142026-04-082026-12-22Active
Form BClinch River BWRX-300Formwork182026-04-152026-11-30Active
Concrete Pour AClinch River BWRX-300Concrete222026-05-012026-11-15Active
Steel Erection AClinch River BWRX-300Structural Steel162026-06-102027-02-28Scheduled
MEP Rough AK Street Garage PourMEP122026-05-202026-08-30Active
Earthwork AHelios Logistics CenterEarthwork102026-03-012026-06-04Rolling off
Finish Trades AHelios Logistics CenterFinishes82026-06-152026-09-12Scheduled
Steel Erection BClinch River BWRX-300Structural Steel142026-05-102026-08-30Delayed

Equipment allocation

AssetDescriptionProjectWindowUtilization
CRN-300T-01Liebherr LR 1750 — 750t crawlerClinch River BWRX-3002026-04-012027-03-3188%
EXC-CAT-390F-01CAT 390F hydraulic excavatorClinch River BWRX-3002026-04-152026-12-1576%
MAN-LIFT-JLG-02JLG 1500SJ boom liftK Street Garage Pour2026-04-222026-08-3064%
GEN-1500KW-01Cummins QSK60 generatorHelios Logistics Center2026-02-012026-07-3092%
DOZ-D9T-03CAT D9T track-type tractorClinch River BWRX-3002026-03-012026-05-180%

Workforce demand

TradeCommittedForecast 30dForecast 90dIn poolContract on-demand
Rebar / Post-tension141418630
Formwork181822412
Concrete222424820
Structural Steel162832418
MEP121824210
Earthwork1064814