6 crews · avg PI 0.93 · CPI 0.96
OVERSIGHT · FIELD PRODUCTIVITY

Crew output & earned value

Weekly crew output reconciled against earned-value cost codes.
6active crews1,800hours / wk0.93avg PI0.96overall CPI1behind2slipping

Crew output — this week

CrewForemanTradeHours / wkOutput / targetPITrend
Rebar ALloyd PattersonRebar / Post-tension36084.2 / 90 tons0.94Slipping
Form BMarcus KelleyFormwork3204,120 / 4,200 SFCA0.98On track
Concrete Pour ASam WhitakerConcrete280612 / 600 CY placed1.02On / over
MEP Rough AYvonne CastroMEP4001,840 / 2,100 LF conduit0.88Slipping
Steel Erection AReggie TinsleyStructural Steel24038 / 40 pcs erected0.95On track
Earthwork ADevin MarcusEarthwork20018,400 / 22,000 BCY moved0.84Behind

Earned progress by cost code

Cost codeDescriptionBudget hrsActual hrsEarned hrsCPI
03-30-00Cast-in-place concrete18,40012,18011,7200.96
03-21-00Reinforcing steel6,2004,4104,1800.95
05-12-00Structural steel — fabrication & erection8,4005,9806,4001.07
31-20-00Earth-moving & rough grading4,8003,2402,7200.84
26-05-00Electrical — power & lighting rough12,4006,1805,4400.88
22-10-00Plumbing & process piping9,2004,9004,8100.98