BUILD · PROGRESS

LIDAR-anchored progress + earned value

8 areas · avg 72% · 2 behind
OVERSIGHT · PROGRESS

LIDAR-anchored progress

Captured % complete, earned value, trade drift, and forecast at completion.
8areas tracked72%avg LIDAR %2ahead2drifting2behind1FAC > BAC

Area-level % complete + trade drift

AreaTradeLIDAR % / Baseline %Drift (days)Forecast / BaselineStatus
Reactor Building — FoundationsConcrete100% / 100%+2d2026-04-10 / 2026-04-12Ahead
Reactor Building — Containment linerSteel / welding48% / 55%-6d2026-09-22 / 2026-09-15Drifting
Turbine Building — Steel erectionStructural Steel91% / 88%+4d2026-06-30 / 2026-07-05Ahead
Turbine Building — MEP rough-inMEP28% / 42%-14d2026-12-20 / 2026-12-05Behind
Control Building — SOGConcrete100% / 100%0d2026-03-22 / 2026-03-22On track
Aux Building — Block wallsMasonry72% / 80%-8d2026-08-12 / 2026-08-04Drifting
Cooling Tower — ExcavationEarthwork38% / 60%-22d2026-08-22 / 2026-08-01Behind
Switchyard — FoundationsCivil100% / 100%-3d2026-04-18 / 2026-04-15On track

Earned value & forecast at completion

ProjectBCWSBCWPACWPSPICPIForecast at CompletionBAC
Clinch River BWRX-300$184.5M$168.4M$176.9M0.910.95$612.8M$598.4M
Helios Logistics Center$62.4M$64.1M$61.3M1.031.05$71.2M$72.4M
K Street Garage Pour$18.4M$19.1M$17.8M1.041.07$33.8M$34.9M