DELIVERY

Daily Log

Build · Daily Log/May 15, 2026

Main Office Tower Excavation — May 15, 2026

DraftAtlanta, GA · MidtownPwC TAGGED#000004 · v1
AM · PMClear·Clear
HIGH (°F)85.0
LOW (°F)66.0
WIND (MPH)4.0
PRECIP (IN)0.00
HUMIDITY %41
SOURCENOAA · GHCND
Manpower28 workers · 224.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Barrett ExcavationMass excavation18144.0Bench 3 cut to el. 102.5; bottom-of-cut surveyed.#000400 · v1
Southern ShoringShoring — soldier piles756.0Lagging at piles 14-19 — eng QC pending.#000401 · v1
Atlanta Survey GroupSurvey / layout324.0BOC + control points shot — log to Trimble.#000402 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Excavator — 50-tonCAT 349 — bench 3 east210.0Barrett ExcavationNormal ops.#000430 · v1
Articulated HaulerVolvo A40G — spoil to off-site440.0Barrett ExcavationManifest 8821-8824 attached.#000431 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
31 23 16.001Mass excavation — Bench 3850905CY144.01.06#000470 · v1
31 41 16.002Soldier pile lagging — bench 387.5EA56.00.94#000471 · v1
Delays0 records
TypeDurationResponsibleDescriptionLinked RFIAudit
No delays recorded for this day.
Deliveries0 records
VendorMaterialQtyUnitDeliveredReceived byAudit
No deliveries logged.
Visitors0 records
NameCompanyPurposeArrivedDepartedAudit
No site visitors today.
General notes
Soldier-pile QC complete piles 14-19; lagging at piles 20-25 begun. Survey reshoot pre-shore set.