Main Office Tower Excavation · May 13, 2026
Project operating path
Atlas Tower
1234 Peachtree St NE, Atlanta GA
Build · Daily Log
/
May 13, 2026
Main Office Tower Excavation — May 13, 2026
Approved
Atlanta, GA · Midtown
PwC TAGGED
#000002 · v3
AM · PM
Cloudy
·
Rain
HIGH (°F)
79.0
LOW (°F)
67.0
WIND (MPH)
11.0
PRECIP (IN)
0.42
HUMIDITY %
78
SOURCE
NOAA · GHCND
Manpower
19 workers · 134.0 manhours
Subcontractor
Trade
Crew
Hours
Notes
Audit
Barrett Excavation
Mass excavation
9
54.0
Dewatering pumps online — 3.4M gal pulled.
#000200 · v1
Southern Shoring
Shoring — soldier piles
7
56.0
Lagging at piles 14-19 — eng QC pending.
#000201 · v1
Atlanta Survey Group
Survey / layout
3
24.0
BOC + control points shot — log to Trimble.
#000202 · v1
Equipment
2 units
Type
Description
Qty
Hours
Operator
Notes
Audit
Excavator — 50-ton
CAT 349 — bench 3 east
2
4.0
Barrett Excavation
Reduced ops — wet conditions.
#000230 · v1
Articulated Hauler
Volvo A40G — spoil to off-site
4
40.0
Barrett Excavation
Manifest 8821-8824 attached.
#000231 · v1
Productivity
2 cost codes
Cost code
Description
Planned
Actual
Unit
MH
PF
Audit
31 23 16.001
Mass excavation — Bench 3
850
412
CY
54.0
0.48
#000270 · v1
31 41 16.002
Soldier pile lagging — bench 3
8
7.5
EA
56.0
0.94
#000271 · v1
Delays
1 record
Type
Duration
Responsible
Description
Linked RFI
Audit
Owner-decision pending
AGENT-FLAGGED
3.0h
Owner — Highland District Sponsors
Bench-3 dewatering plan awaiting Owner geotech sign-off; pumps held east half.
RFI-MOT-0078
#000002 · v1
Deliveries
0 records
Vendor
Material
Qty
Unit
Delivered
Received by
Audit
No deliveries logged.
Visitors
0 records
Name
Company
Purpose
Arrived
Departed
Audit
No site visitors today.
General notes
Rain afternoon — dewatering pumps to 3.4M gal pulled. Owner geotech sign-off pending for east-half dewatering plan; flagged for AM call.