DELIVERY

Daily Log

Build · Daily Log/May 13, 2026

Main Office Tower Excavation — May 13, 2026

ApprovedAtlanta, GA · MidtownPwC TAGGED#000002 · v3
AM · PMCloudy·Rain
HIGH (°F)79.0
LOW (°F)67.0
WIND (MPH)11.0
PRECIP (IN)0.42
HUMIDITY %78
SOURCENOAA · GHCND
Manpower19 workers · 134.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Barrett ExcavationMass excavation954.0Dewatering pumps online — 3.4M gal pulled.#000200 · v1
Southern ShoringShoring — soldier piles756.0Lagging at piles 14-19 — eng QC pending.#000201 · v1
Atlanta Survey GroupSurvey / layout324.0BOC + control points shot — log to Trimble.#000202 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Excavator — 50-tonCAT 349 — bench 3 east24.0Barrett ExcavationReduced ops — wet conditions.#000230 · v1
Articulated HaulerVolvo A40G — spoil to off-site440.0Barrett ExcavationManifest 8821-8824 attached.#000231 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
31 23 16.001Mass excavation — Bench 3850412CY54.00.48#000270 · v1
31 41 16.002Soldier pile lagging — bench 387.5EA56.00.94#000271 · v1
Delays1 record
TypeDurationResponsibleDescriptionLinked RFIAudit
Owner-decision pendingAGENT-FLAGGED3.0hOwner — Highland District SponsorsBench-3 dewatering plan awaiting Owner geotech sign-off; pumps held east half.RFI-MOT-0078#000002 · v1
Deliveries0 records
VendorMaterialQtyUnitDeliveredReceived byAudit
No deliveries logged.
Visitors0 records
NameCompanyPurposeArrivedDepartedAudit
No site visitors today.
General notes
Rain afternoon — dewatering pumps to 3.4M gal pulled. Owner geotech sign-off pending for east-half dewatering plan; flagged for AM call.