Build · Daily Log/May 12, 2026

Main Office Tower Excavation — May 12, 2026

ApprovedAtlanta, GA · MidtownPwC TAGGED#000001 · v3
AM · PMPartly Cloudy·Partly Cloudy
HIGH (°F)84.0
LOW (°F)65.0
WIND (MPH)5.0
PRECIP (IN)0.00
HUMIDITY %49
SOURCENOAA · GHCND
Manpower28 workers · 224.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Barrett ExcavationMass excavation18144.0Bench 3 cut to el. 102.5; bottom-of-cut surveyed.#000100 · v1
Southern ShoringShoring — soldier piles756.0Lagging at piles 14-19 — eng QC pending.#000101 · v1
Atlanta Survey GroupSurvey / layout324.0BOC + control points shot — log to Trimble.#000102 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Excavator — 50-tonCAT 349 — bench 3 east210.0Barrett ExcavationNormal ops.#000130 · v1
Articulated HaulerVolvo A40G — spoil to off-site440.0Barrett ExcavationManifest 8821-8824 attached.#000131 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
31 23 16.001Mass excavation — Bench 3850905CY144.01.06#000170 · v1
31 41 16.002Soldier pile lagging — bench 387.5EA56.00.94#000171 · v1
Delays0 records
TypeDurationResponsibleDescriptionLinked RFIAudit
No delays recorded for this day.
Deliveries1 record
VendorMaterialQtyUnitDeliveredReceived byAudit
Atlas Stone & AggregateCrushed stone #57 — base course240TON7:22 AM UTCP. Mirahmadi#000001 · v1
Visitors1 record
NameCompanyPurposeArrivedDepartedAudit
J. WexlerPeachtree Capital PartnersMonthly owner walk-through1:05 PM UTC2:42 PM UTC#000001 · v1
General notes
Aggregate base course delivery — 240 TON #57 (manifests A22-104 through A22-108). Soldier-pile lagging continuing piles 14-19.