Main Office Tower Excavation · May 12, 2026
Project operating path
Atlas Tower
1234 Peachtree St NE, Atlanta GA
Build · Daily Log
/
May 12, 2026
Main Office Tower Excavation — May 12, 2026
Approved
Atlanta, GA · Midtown
PwC TAGGED
#000001 · v3
AM · PM
Partly Cloudy
·
Partly Cloudy
HIGH (°F)
84.0
LOW (°F)
65.0
WIND (MPH)
5.0
PRECIP (IN)
0.00
HUMIDITY %
49
SOURCE
NOAA · GHCND
Manpower
28 workers · 224.0 manhours
Subcontractor
Trade
Crew
Hours
Notes
Audit
Barrett Excavation
Mass excavation
18
144.0
Bench 3 cut to el. 102.5; bottom-of-cut surveyed.
#000100 · v1
Southern Shoring
Shoring — soldier piles
7
56.0
Lagging at piles 14-19 — eng QC pending.
#000101 · v1
Atlanta Survey Group
Survey / layout
3
24.0
BOC + control points shot — log to Trimble.
#000102 · v1
Equipment
2 units
Type
Description
Qty
Hours
Operator
Notes
Audit
Excavator — 50-ton
CAT 349 — bench 3 east
2
10.0
Barrett Excavation
Normal ops.
#000130 · v1
Articulated Hauler
Volvo A40G — spoil to off-site
4
40.0
Barrett Excavation
Manifest 8821-8824 attached.
#000131 · v1
Productivity
2 cost codes
Cost code
Description
Planned
Actual
Unit
MH
PF
Audit
31 23 16.001
Mass excavation — Bench 3
850
905
CY
144.0
1.06
#000170 · v1
31 41 16.002
Soldier pile lagging — bench 3
8
7.5
EA
56.0
0.94
#000171 · v1
Delays
0 records
Type
Duration
Responsible
Description
Linked RFI
Audit
No delays recorded for this day.
Deliveries
1 record
Vendor
Material
Qty
Unit
Delivered
Received by
Audit
Atlas Stone & Aggregate
Crushed stone #57 — base course
240
TON
7:22 AM UTC
P. Mirahmadi
#000001 · v1
Visitors
1 record
Name
Company
Purpose
Arrived
Departed
Audit
J. Wexler
Peachtree Capital Partners
Monthly owner walk-through
1:05 PM UTC
2:42 PM UTC
#000001 · v1
General notes
Aggregate base course delivery — 240 TON #57 (manifests A22-104 through A22-108). Soldier-pile lagging continuing piles 14-19.