Daily Log
K St Garage Pour · May 15, 2026Project operating path
K St Garage Pour — May 15, 2026
DraftWashington, DC · West EndPwC TAGGED#000004 · v1
AM · PMClear·Clear
HIGH (°F)76.0
LOW (°F)59.0
WIND (MPH)5.0
PRECIP (IN)0.00
HUMIDITY %38
SOURCENOAA · GHCND
| Subcontractor | Trade | Crew | Hours | Notes | Audit |
|---|---|---|---|---|---|
| Pinnacle Concrete Co. | Concrete — Slab on Deck | 22 | 176.0 | Pour 14B — 162 CY 5,000-psi. Slump tickets attached. | #000400 · v1 |
| Liberty Rebar & Post-Tension | Rebar — placement | 11 | 88.0 | Mat tied for pour 14C. | #000401 · v1 |
| Capitol Electric | Electrical — rough-in | 6 | 48.0 | Conduit runs B3 east — coordinated with Sprinkler. | #000402 · v1 |
| Type | Description | Qty | Hours | Operator | Notes | Audit |
|---|---|---|---|---|---|---|
| Concrete Pump — 47m boom | Schwing S 47 SX — west side ramp | 1 | 8.0 | Pinnacle Concrete Co. | All clear. | #000430 · v1 |
| Tower Crane TC-1 | Liebherr 280 EC-H — 60m radius | 1 | 10.0 | Self-perform | DOL daily inspection complete. | #000431 · v1 |
| Cost code | Description | Planned | Actual | Unit | MH | PF | Audit |
|---|---|---|---|---|---|---|---|
| 03 30 00.001 | Concrete — slab on deck — 5,000 psi | 160 | 162 | CY | 176.0 | 1.01 | #000470 · v1 |
| 03 21 00.002 | Rebar — tied #5 mat | 2.2 | 2.1 | TON | 88.0 | 0.95 | #000471 · v1 |
| Type | Duration | Responsible | Description | Linked RFI | Audit |
|---|---|---|---|---|---|
| No delays recorded for this day. | |||||
| Vendor | Material | Qty | Unit | Delivered | Received by | Audit |
|---|---|---|---|---|---|---|
| Liberty Rebar & Post-Tension | PT tendons — 0.6" Grade 270 (bundle 14C) | 1.4 | TON | 7:38 AM UTC | M. Castillo | #000004 · v1 |
| Name | Company | Purpose | Arrived | Departed | Audit |
|---|---|---|---|---|---|
| No site visitors today. | |||||
Pour 14C readied — PT tendons delivered 7:38a. Pre-pour walk-through with Owner Rep at 11:00a.