DELIVERY

Daily Log

Build · Daily Log/May 14, 2026

K St Garage Pour — May 14, 2026

SubmittedWashington, DC · West EndPwC TAGGED#000003 · v2
AM · PMCloudy·Partly Cloudy
HIGH (°F)68.0
LOW (°F)57.0
WIND (MPH)9.0
PRECIP (IN)0.04
HUMIDITY %66
SOURCENOAA · GHCND
Manpower39 workers · 312.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Pinnacle Concrete Co.Concrete — Slab on Deck22176.0Pour 14B — 162 CY 5,000-psi. Slump tickets attached.#000300 · v1
Liberty Rebar & Post-TensionRebar — placement1188.0Mat tied for pour 14C.#000301 · v1
Capitol ElectricElectrical — rough-in648.0Conduit runs B3 east — coordinated with Sprinkler.#000302 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Concrete Pump — 47m boomSchwing S 47 SX — west side ramp18.0Pinnacle Concrete Co.All clear.#000330 · v1
Tower Crane TC-1Liebherr 280 EC-H — 60m radius110.0Self-performDOL daily inspection complete.#000331 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
03 30 00.001Concrete — slab on deck — 5,000 psi160162CY176.01.01#000370 · v1
03 21 00.002Rebar — tied #5 mat2.21.62TON92.00.74#000371 · v1
Delays0 records
TypeDurationResponsibleDescriptionLinked RFIAudit
No delays recorded for this day.
Deliveries0 records
VendorMaterialQtyUnitDeliveredReceived byAudit
No deliveries logged.
Visitors1 record
NameCompanyPurposeArrivedDepartedAudit
Insp. R. AokiDC DOB — Concrete inspectionCylinder break observation10:00 AM UTC11:15 AM UTC#000003 · v1
General notes
Cleanup + re-screed of slab 14B east. Productivity on rebar mat down (PF 0.74); investigating splice density vs spec.