Build · Daily Log/May 13, 2026

K St Garage Pour — May 13, 2026

ApprovedWashington, DC · West EndPwC TAGGED#000002 · v3
AM · PMRain·Heavy Rain
HIGH (°F)62.0
LOW (°F)55.0
WIND (MPH)14.0
PRECIP (IN)1.34
HUMIDITY %88
SOURCENOAA · GHCND
Manpower18 workers · 116.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Pinnacle Concrete Co.Concrete — Slab on Deck848.0Stopped pour at 11:14a — water-cement ratio risk per spec 03 30 00 §3.07.#000200 · v1
Liberty Rebar & Post-TensionRebar — placement420.0Tied tendons under cover.#000201 · v1
Capitol ElectricElectrical — rough-in648.0Conduit runs B3 east — coordinated with Sprinkler.#000202 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Concrete Pump — 47m boomSchwing S 47 SX — west side ramp12.5Pinnacle Concrete Co.Stowed for storm.#000230 · v1
Tower Crane TC-1Liebherr 280 EC-H — 60m radius110.0Self-performDOL daily inspection complete.#000231 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
03 30 00.001Concrete — slab on deck — 5,000 psi00CY48.0#000270 · v1
03 21 00.002Rebar — tied #5 mat2.22.1TON88.00.95#000271 · v1
Delays1 record
TypeDurationResponsibleDescriptionLinked RFIAudit
Weather — heavy rainAGENT-FLAGGED6.5hForce majeurePour 14B halted at 11:14a per ACI 305R cold-rain limit; cleanup + re-screed scheduled 2026-05-14.RFI-KST-0142#000002 · v1
Deliveries0 records
VendorMaterialQtyUnitDeliveredReceived byAudit
No deliveries logged.
Visitors0 records
NameCompanyPurposeArrivedDepartedAudit
No site visitors today.
General notes
Severe rain — pour 14C postponed. ACI 305R cold-rain protocol invoked at 11:14a. Re-screed scheduled 2026-05-14.