Build · Daily Log/May 12, 2026

K St Garage Pour — May 12, 2026

ApprovedWashington, DC · West EndPwC TAGGED#000001 · v3
AM · PMPartly Cloudy·Cloudy
HIGH (°F)71.0
LOW (°F)60.0
WIND (MPH)8.0
PRECIP (IN)0.00
HUMIDITY %53
SOURCENOAA · GHCND
Manpower39 workers · 312.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Pinnacle Concrete Co.Concrete — Slab on Deck22176.0Pour 14B — 162 CY 5,000-psi. Slump tickets attached.#000100 · v1
Liberty Rebar & Post-TensionRebar — placement1188.0Mat tied for pour 14C.#000101 · v1
Capitol ElectricElectrical — rough-in648.0Conduit runs B3 east — coordinated with Sprinkler.#000102 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Concrete Pump — 47m boomSchwing S 47 SX — west side ramp18.0Pinnacle Concrete Co.All clear.#000130 · v1
Tower Crane TC-1Liebherr 280 EC-H — 60m radius110.0Self-performDOL daily inspection complete.#000131 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
03 30 00.001Concrete — slab on deck — 5,000 psi160162CY176.01.01#000170 · v1
03 21 00.002Rebar — tied #5 mat2.22.1TON88.00.95#000171 · v1
Delays0 records
TypeDurationResponsibleDescriptionLinked RFIAudit
No delays recorded for this day.
Deliveries0 records
VendorMaterialQtyUnitDeliveredReceived byAudit
No deliveries logged.
Visitors1 record
NameCompanyPurposeArrivedDepartedAudit
J. WexlerPeachtree Capital PartnersMonthly owner walk-through1:05 PM UTC2:42 PM UTC#000001 · v1
General notes
Owner walk-through 1:05p-2:42p. Punch items: handrail return on Stair B3 (open) and exposed conduit at column line E-7 (closed same-day).