K St Garage Pour — May 11, 2026

ApprovedWashington, DC · West EndPwC TAGGED#000000 · v3
AM · PMClear·Partly Cloudy
HIGH (°F)74.0
LOW (°F)58.0
WIND (MPH)6.0
PRECIP (IN)0.00
HUMIDITY %41
SOURCENOAA · GHCND
Manpower39 workers · 312.0 manhours
SubcontractorTradeCrewHoursNotesAudit
Pinnacle Concrete Co.Concrete — Slab on Deck22176.0Pour 14B — 162 CY 5,000-psi. Slump tickets attached.#000000 · v1
Liberty Rebar & Post-TensionRebar — placement1188.0Mat tied for pour 14C.#000001 · v1
Capitol ElectricElectrical — rough-in648.0Conduit runs B3 east — coordinated with Sprinkler.#000002 · v1
Equipment2 units
TypeDescriptionQtyHoursOperatorNotesAudit
Concrete Pump — 47m boomSchwing S 47 SX — west side ramp18.0Pinnacle Concrete Co.All clear.#000030 · v1
Tower Crane TC-1Liebherr 280 EC-H — 60m radius110.0Self-performDOL daily inspection complete.#000031 · v1
Productivity2 cost codes
Cost codeDescriptionPlannedActualUnitMHPFAudit
03 30 00.001Concrete — slab on deck — 5,000 psi160162CY176.01.01#000070 · v1
03 21 00.002Rebar — tied #5 mat2.22.1TON88.00.95#000071 · v1
Delays0 records
TypeDurationResponsibleDescriptionLinked RFIAudit
No delays recorded for this day.
Deliveries1 record
VendorMaterialQtyUnitDeliveredReceived byAudit
MMC Materials — DC depotConcrete 5,000-psi (Mix #C5K-2)162CY8:14 AM UTCM. Castillo#000000 · v1
Visitors0 records
NameCompanyPurposeArrivedDepartedAudit
No site visitors today.
General notes
Pour 14B complete on plan — 162 CY 5,000-psi. 28-day cylinders pulled per spec 03 30 00 §3.05.