Slump test 4.5" — within tolerance. 4 cylinders cast for 28-day break.
Jobsite Photos
12 of 12 captures · grouped by day
Sun, May 17, 2026
4 captures8" CHWS main hanger spacing — out of spec at gridline F12, flagged.
Perimeter beam W14x90 — full-pen welds at column line G complete.
South bay rebar mat post-tie inspection — ready for pre-pour walk.
Sat, May 16, 2026
3 capturesAHU-7 delivered to penthouse via tower crane, staged for set.
Plumb check at column F-12 — within 1/4" of vertical tolerance.
4000A switchgear lineup arrived on site, awaiting rigging plan signoff.
Fri, May 15, 2026
2 capturesConduit routing conflict at gridline H7 — needs coordination with HVAC.
Shoring re-shore configuration at column line C — per RFI 197 response.
Thu, May 14, 2026
1 captureBolt-up at gridline B/9 — torque verification logs attached.
Wed, May 13, 2026
2 capturesCooling tower pad excavation — sub-base proof rolled, ready for rebar.
Tower crane monthly third-party inspection — passed, cert posted.