K Street Garage Pour · 415 K Street NW, Atlanta, GA 30308
5-phase ledger · design review → install verify → startup → functional test → training · as of 2026-05-17
Cx completion68%17 / 25 phase-checkpoints complete
Assets51 fully cx'd
Defects41 retest pending · 2 high/critical
Cx reports40 final issued
First-pass yield0%defects passing first retest
| Asset | System | Class | Cx phases | Audit |
|---|
| AHU-01 | Air handling (level 1) | Air handler — 8,000 CFM | DesignInstallStartupFunctionalTraining | evt_cx_k_001 |
| AHU-02 | Air handling (level 2-3) | Air handler — 12,000 CFM | DesignInstallStartupFunctionalTraining | evt_cx_k_002 |
| SWGR-MDP1 | Main distribution panel | Switchgear — 2500A 480V | DesignInstallStartupFunctionalTraining | evt_cx_k_003 |
| FP-PUMP-01 | Fire pump room | Electric fire pump — 1000gpm | DesignInstallStartupFunctionalTraining | evt_cx_k_004 |
| EVSE-BANK-A | Level 2 charger bank A | EV charger — 32x ChargePoint CP6000 | DesignInstallStartupFunctionalTraining | evt_cx_k_005 |
| ID | Asset | Found | Description | Severity | Finder | Action | 1st | 2nd | Final |
|---|
| def-001 | AHU-01 | 2026-04-09 | Supply-air temp setpoint reset schedule inverted vs. sequence. | moderate | TAB Agent — BlueLine Cx | BMS reprogrammed; reset polarity corrected. | fail | pass | pass |
| def-002 | SWGR-MDP1 | 2026-04-15 | Phase A trip pickup 1.04× nameplate; outside +/-1% tolerance. | high | Cx Agent — Resolution Engineering | TCC curves resubmitted; relay re-calibrated by EATON. | fail | pending | pending |
| def-003 | EVSE-BANK-A | 2026-04-19 | OCPP cloud handshake intermittent at 4 of 32 chargers. | moderate | Cx Agent — Resolution Engineering | Modem firmware bumped; antenna gain repositioned. | fail | pass | pass |
| def-004 | AHU-02 | 2026-03-28 | VFD harmonic distortion 9.4% — exceeds IEEE-519 5% limit. | critical | TAB Agent — BlueLine Cx | Line reactor installed upstream of VFD. | fail | pass | pass |
FAT2026-02-12
Factory Acceptance — Eaton MDP-1
Factory Acceptance
Issued by Eaton — Pittsburgh
k-street/cx/FAT-MDP1.pdfevt_rep_k_001
SAT2026-04-04
Site Acceptance — AHU 1-3
Site Acceptance
Issued by BlueLine Cx
k-street/cx/SAT-AHU.pdfevt_rep_k_002
TAB2026-04-18
Test, Adjust, Balance Final — HVAC
Test, Adjust & Balance
Issued by BlueLine Cx
k-street/cx/TAB-FINAL.pdfevt_rep_k_003
IST2026-04-15
Integrated Systems Test — Fire/Egress/Smoke
Integrated Systems
Issued by Resolution Engineering
k-street/cx/IST-FIRE.pdfevt_rep_k_004