| Sign-off | AIA G704 — Substantial Completion (K Street) | K Street Garage Pour | Fully executed | Brookfield K Street LLC | 2026-04-22 | Open → |
| Inspection | TCO Final Walk — City of Atlanta DPCD | K Street Garage Pour | Scheduled · 2026-05-23 | Bureau of Buildings | 2026-05-23 | Open → |
| Punch | Architectural punch — 47 of 62 closed | K Street Garage Pour | In progress | Cooper Carry A/E + subs | 2026-05-19 | Open → |
| Deliverable | O&M Manual Vol. 1 — HVAC & BMS | K Street Garage Pour | Submitted · awaiting accept | Brookfield K Street Ops | 2026-05-04 | Open → |
| Warranty | Switchgear warranty (24 mo) — clock started | K Street Garage Pour | Active · 706d remaining | Eaton — Pittsburgh | 2026-04-22 | Open → |
| Sign-off | AIA G704 — Substantial Completion (Helios) | Helios Logistics Center | Fully executed | Helios Industrial Partners LP | 2026-03-08 | Open → |
| Inspection | Certificate of Occupancy — Clayton County | Helios Logistics Center | Pending CO visit | Clayton County Building Safety | 2026-05-22 | Open → |
| Deliverable | Helios Final Acceptance Walk Letter | Helios Logistics Center | Out for signature | Helios Industrial Partners LP | 2026-05-12 | Open → |
| Warranty | ESFR sprinkler warranty (24 mo) | Helios Logistics Center | Active · 660d remaining | FireOps GC | 2026-03-08 | Open → |
| Punch | Cx defect — MDP-1 phase A trip outside ±1% | K Street Garage Pour | Retest pending — EATON | Resolution Engineering | 2026-04-15 | Open → |
| Deliverable | As-built — M-301 HVAC L2 (rev R7) | K Street Garage Pour | In redline | Stanley Beaman & Sears MEP | 2026-05-08 | Open → |
| Sign-off | Warranty Commencement Notice (Helios) | Helios Logistics Center | Fully executed | Helios Industrial Partners LP | 2026-03-08 | Open → |