BUILD · WORKFORCE

Workforce

136 on site today · 11 contractors · 17 crews · captured Sun, May 17, 12:00 PM

On site today
136·0vs yesterday
Active contractors
11
Active crews
17
Trades represented
11

Trade rollup

Today's headcount with 7-day trend

TradeTodayΔ vs yest.7-day trendCrewsAudit ID
Concrete24+23wft_concrete
Electrical22+22wft_electrical
General / Site18+12wft_general
Structural Steel1621wft_structural_steel
HVAC / Mechanical14+12wft_mechanical
Drywall / Framing1222wft_drywall
Plumbing811wft_plumbing
Carpentry / Finishes7+11wft_carpentry
Earthwork / Sitework621wft_earthwork
Masonry5·01wft_masonry
Roofing / Waterproofing4·01wft_roofing

Contractor crew detail

16 crews
ContractorTradeSupervisorHeadcountAreaStatusAudit ID
Envision Construction GCGeneral / SiteJordan Ellis18Site-wideSupt. + logistics + safety + QA + GC staffwfc_meridian_gc
Apex Steel ErectorsStructural SteelKayla Reeves16Level 12 — perimeterBolt-up at gridline G; topped out yesterdaywfc_apex_steel
Olson Concrete & FormingConcreteDaniel Olson14Level B2 — south bay slabPouring 4500 PSI mat slab, pour #14wfc_olson_concrete_a
Voltline ElectricElectricalHector Diaz14Level 04 — MEP rough-inPulling conduit feeders to RPP-4Awfc_volt_electrical_a
Aircore MechanicalHVAC / MechanicalWei-Ling Tang9Roof — AHU padsSetting AHU-1 isolation padswfc_aircore_mech
Voltline ElectricElectricalRobin Carthy8Switchgear vault — Level B24000A switchgear staging + LOTOwfc_volt_electrical_b
Hydra Plumbing Co.PlumbingTravis Aldridge8Level 05 — risersSanitary risers at zone Bwfc_hydra_plumb
Sheetwall InteriorsDrywall / FramingPriscilla Owens8Level 07 — drywall hangHanging 5/8 type-X at corridorswfc_sheetwall_drywall_a
Meridian CarpentryCarpentry / FinishesOwen Briggs7Lobby — millwork prepField-fit walnut casework, lobby receptionwfc_meridian_carp
Olson Concrete & FormingConcreteReginald Pierce6Level 04 — column formsStripping forms, prepping column line Gwfc_olson_concrete_b
Groundline ExcavationEarthwork / SiteworkLila Mendoza6Site — east trenchTrenching for storm lateral SL-3wfc_groundline_earth
Aircore MechanicalHVAC / MechanicalCasey Hwang5Level 07 — VAV installHanging VAVs, branch ductworkwfc_aircore_mech_b
Lithos MasonryMasonryGreta Sundholm5Lobby — limestone veneerSetting limestone band course at storefrontwfc_lithos_masonry
Olson Concrete & FormingConcreteMarcus Vaughn4Level 03 — rebar tyingTying #8 bars at typical bay layoutwfc_olson_concrete_c
Sheetwall InteriorsDrywall / FramingTheo Brennan4Level 06 — tapingLevel-4 tape + skim at residential corridorwfc_sheetwall_drywall_b
Topshield RoofingRoofing / WaterproofingAnwar Khaled4Roof — north quadrantHot-mop application on TPO underlaymentwfc_topshield_roof