CSI MasterFormat estimates, UniFormat crosswalk, burn rate by division, and GMP validation.

Delta

+$2.8M

vs. feasibility basis

Risk divisions

03 / 07 / 09

high movement

GMP confidence

78%

basis maturity

Burn rate

$420K/wk

preconstruction spend

Active Work

Live CSI-coded estimate movement, UniFormat crosswalk, burn-rate exposure, and GMP validation.

CSI estimates

97%

coded by division

UniFormat crosswalk

88%

feasibility bridge

GMP validation

78%

scope gaps remain

Provenance & Lineage

Will the design land at or below the GMP basis?

System of record
services/live-cost-feedback + project read model
Upstream modules
Feasibility, Pro Forma, Design Coordination, Scope Discipline
Downstream modules
Scope Discipline, Procurement, Budget

Module views

CSI MasterFormat EstimatesUniFormat CrosswalkBurn Rate by DivisionGMP Validation

Cost movement

SubjectOwnerBasisStatus
07 EnvelopeEstimating+$1.4MValidate
03 ConcreteStructural+$820KConfirmed
12 FFEDesign-$340KAccepted

Project Context

South Harbor (SH-2042) · Savannah

Next action: RFI-0142 door head detail

  • GMP confidence

    82%

    8-quarter trend

  • Schedule float

    12d

    vs baseline

  • Burn rate

    $1.4M/wk

    8-week

  • Cost-to-complete

    $48M

    Trending down

CodeBucketFeasibilityEstimateDelta $Delta %Status
03Concrete$12,400,000$12,700,000+$300,000+2.4%Over
23HVAC$8,900,000$9,200,000+$300,000+3.4%Over
26Electrical$6,700,000$6,900,000+$200,000+3.0%Over
Total · 3 buckets$28,000,000$28,800,000+$800,000