K Street Garage Pour · 415 K Street NW, Atlanta, GA 30308
Substantial completion · 2026-04-22 · as of 2026-05-17
Handover92%punch open
Punch resolved12/183 open · 2 ready for verify · 1 reopened
Inspections2/42 pending
Signoffs1/32 outstanding
Warranty earliest340dto first expiration
Punch-out checklist

Areas → items → status

18 items · 13 areas in-scope
Level 2 — Bay 14Level 2 — Stair BLevel 3 — Bay 21Level 1 — LobbyRoof — Mech YardLevel 1 — Bay 02Level 2 — Bay 09Level 3 — Stair ALevel 1 — Bay 14Level 2 — Bay 17Level 2 — Bay 02Level 3 — Bay 09Level 1 — Bay 22
IDAreaDescriptionDisciplineStatusAssigneeAgePhotosAudit
punch-001Level 2 — Bay 14Concrete spall at deck edge; repair + recoat.StructuralOpenStressCrete Inc.6d3evt_punch_k_00…
punch-002Level 2 — Stair BHandrail return missing per IBC 1014.6.ArchitecturalReady for verifySouthern Steel Fabricators4d2evt_punch_k_00…
punch-003Level 3 — Bay 21EV charger conduit landing 14ga short; replace + tag.ElecOpenRedMark Electric9d4evt_punch_k_00…
punch-004Level 1 — LobbyAcoustic tile field cuts uneven, NE corner.ArchitecturalOpenSouthern Ceilings & Drywall11d5evt_punch_k_00…
punch-005Roof — Mech YardAHU-3 condensate trap inverted vs. plan SP-201.MechReady for verifyBlueLine Mechanical3d2evt_punch_k_00…
punch-006Level 1 — Bay 02FP sprinkler escutcheon 4 missing; install + paint.FPReopenedFirewatch Suppression14d1evt_punch_k_00…
punch-007Level 2 — Bay 09Curb stop crack at column line C7.CivilVerifiedStressCrete Inc.18d3evt_punch_k_00…
punch-008Level 3 — Stair ANosing reflectivity strip missing on 4 risers.ArchitecturalVerifiedSouthern Steel Fabricators21d1evt_punch_k_00…
punch-009Level 1 — Bay 14Domestic water line lacks dielectric union at brass-iron.PlumbVerifiedClaymore Plumbing Co.12d2evt_punch_k_00…
punch-010Level 2 — Bay 17EM lighting battery test card missing date stamp.ElecVerifiedRedMark Electric16d1evt_punch_k_01…
punch-011Roof — Mech YardRoof curb flashing tear at AHU-1 NW corner.ArchitecturalClosedCoastal Roofing24d4evt_punch_k_01…
punch-012Level 1 — LobbyDoor 101A undercut clearance 5/16" exceeds spec.ArchitecturalClosedSouthern Doors & Hardware27d2evt_punch_k_01…
punch-013Level 2 — Bay 02Floor drain elevation 1/2" high vs. SP-301 grading.CivilClosedStressCrete Inc.31d3evt_punch_k_01…
punch-014Level 3 — Bay 09Joint sealant adhesion failure at 4 control joints.ArchitecturalClosedSealTech Specialties35d6evt_punch_k_01…
punch-015Roof — Mech YardFP standpipe relief test card missing initials.FPClosedFirewatch Suppression41d1evt_punch_k_01…
punch-016Level 1 — Bay 22Light fixture aim tolerance > 10° off-design.ElecClosedRedMark Electric44d2evt_punch_k_01…
punch-017Level 2 — Stair BSlip-resistance test below ASTM E303 BPN-50 minimum.ArchitecturalClosedStressCrete Inc.47d3evt_punch_k_01…
punch-018Roof — Mech YardAHU-2 belt tensioner half-turn loose; tighten + verify.MechClosedBlueLine Mechanical52d1evt_punch_k_01…
TCO / CO checklist

Jurisdiction inspections

Per-AHJ acceptance + next-visit schedule
JurisdictionInspectionStatusLastNextNote
City of Atlanta DPCD — Bureau of BuildingsTCO Final Walkscheduled2026-04-302026-05-23Pre-walk corrections list issued; 6 items pending verify.
Atlanta Fire Rescue Dept. (AFRD)Sprinkler + Standpipe Acceptancepassed with correction2026-04-18Passed with re-tag on FP-3 standpipe relief; signed off.
GA Department of Public HealthPotable Water Cross-Connectionpassed2026-04-09All RPZ devices tested + stamped; report on file.
Fulton County — Environmental HealthSWPPP Final + NOTin progress2026-04-252026-05-19NOT filed; awaiting stabilization sign-off photo set.
Owner acceptance

Signoff stack

AIA G704 + final acceptance + warranty commencement

Certificate of Substantial Completion (AIA G704)

Fully executed
Brookfield K Street LLC
Executed2026-04-22DocuSignds_env_a1f4-K-G704Auditevt_sig_k_001

Final Acceptance — Owner Walk Letter

Drafted
Brookfield K Street LLC
ExecutedDocuSignds_env_b2c5-K-FINALAuditevt_sig_k_002

Warranty Commencement Notice

Drafted
Brookfield K Street LLC
ExecutedDocuSignds_env_c3d6-K-WARRAuditevt_sig_k_003
Warranty start dates

System → start → expiration

Days remaining flagged < 90d
SystemStartTerm (mo)ExpiresDays remaining
HVAC (AHU 1-3, RTU 1-2)2026-04-22122027-04-22340d
Electrical switchgear2026-04-22242028-04-22706d
Roof — single-ply TPO2026-04-222402046-04-227280d
Vertical transport (2 cab)2026-04-22122027-04-22340d