| RFI # | Title | Spec | Status | Ball in court | Due | Cost impact |
|---|---|---|---|---|---|---|
| RFI-0144 | Roof drain RD-4 setting — confirm 1/4"/ft slope to overflow | 22 14 23 | Pending | Henderson MEP Engineers | 18d late | — |
| RFI-0151 | Transformer pad anchor bolt template — verify pattern T2-A | 26 12 19 | Pending | Henderson MEP Engineers | 20d late | $5,400.00no schedule hitUSD |