Open RFIs4Ball-in-court today
Schedule variance-3dCritical path vs baseline
Budget variance+$0.34MForecast vs revised
Open commitments3Subs + POs in flight
Open punch8
Safety open2Investigations + recordables
Daily logs (wk)9
ACROSS ALL PROJECTS

Cockpit register

Every actionable BUILD-stage item — click through to the module.
19 items across 2 active projects · reference date 2026-05-23
KindItemProjectStatusAssigneeDate
RFIRFI 142 — Slab edge condition at column line C/7K Street Garage PourOpen · ball-in-court: A/ECooper Carry A/E2026-05-18Open →
RFIRFI 145 — Conduit penetration spec vs UL 1479K Street Garage PourOpen · ball-in-court: GCEnvision MEP2026-05-21Open →
RFIRFI 089 — Tilt panel embed plate alternativeHelios Logistics CenterOpen · awaiting structuralWalter P Moore2026-05-22Open →
RFIRFI 092 — Dock seal width toleranceHelios Logistics CenterOpen · ball-in-court: A/ECooper Carry A/E2026-05-19Open →
ScheduleA3120 · Core wall pour L4 — 3d behind, on critical pathK Street Garage PourAt risk · float -3dBrasfield & Gorrie2026-05-26Open →
ScheduleA4012 · Tilt-up panel set Bay 7-12 — float consumedHelios Logistics CenterAt risk · float -1dARCO Construction2026-05-25Open →
ScheduleA5210 · Switchgear energization milestoneK Street Garage PourScheduled · 2026-05-30Eaton FSE2026-05-30Open →
CommitmentSC-K042 · Storefront glazing — pending owner execK Street Garage PourOut for signatureBrookfield K Street LLC2026-05-20Open →
CommitmentPO-H311 · ESFR sprinkler heads (1,420 units)Helios Logistics CenterIssued · awaiting deliveryFireOps GC2026-05-22Open →
CommitmentSC-K047 · Elevator commissioning add-svcK Street Garage PourDrafted · pending reviewThyssenKrupp2026-05-19Open →
Submittal08 41 13.04 · Storefront shop drawings (rev 3)K Street Garage PourOut for review · A/ECooper Carry A/E2026-05-21Open →
Submittal23 73 13.01 · AHU-2 product data + warrantyHelios Logistics CenterApproved as notedTrane SE2026-05-17Open →
DrawingA-301 rev 5 — L4 plan, dimensional cleanupK Street Garage PourPending reviewStanley Beaman & Sears2026-05-22Open →
DrawingS-201 rev 3 — Helios tilt panel revisionsHelios Logistics CenterPending reviewWalter P Moore2026-05-20Open →
SafetyNear-miss · ironworker swung pipe at L3 SE cornerK Street Garage PourInvestigation openSite safety supervisor2026-05-22Open →
SafetyRecordable · finger laceration, drywall L2 northK Street Garage PourOSHA 300 loggedEHS — Envision2026-05-15Open →
PunchCeiling grid alignment — L4 East corridor (8 items)K Street Garage PourOpen · 8 itemsDrywall sub2026-05-21Open →
Daily logDaily log 2026-05-22 — K Street crew, weather, notesK Street Garage PourSubmittedField super (M. Reyes)2026-05-22Open →
Daily logDaily log 2026-05-22 — Helios crew, weather, notesHelios Logistics CenterSubmittedField super (J. Tan)2026-05-22Open →