| RFI | RFI 142 — Slab edge condition at column line C/7 | K Street Garage Pour | Open · ball-in-court: A/E | Cooper Carry A/E | 2026-05-18 | Open → |
| RFI | RFI 145 — Conduit penetration spec vs UL 1479 | K Street Garage Pour | Open · ball-in-court: GC | Envision MEP | 2026-05-21 | Open → |
| RFI | RFI 089 — Tilt panel embed plate alternative | Helios Logistics Center | Open · awaiting structural | Walter P Moore | 2026-05-22 | Open → |
| RFI | RFI 092 — Dock seal width tolerance | Helios Logistics Center | Open · ball-in-court: A/E | Cooper Carry A/E | 2026-05-19 | Open → |
| Schedule | A3120 · Core wall pour L4 — 3d behind, on critical path | K Street Garage Pour | At risk · float -3d | Brasfield & Gorrie | 2026-05-26 | Open → |
| Schedule | A4012 · Tilt-up panel set Bay 7-12 — float consumed | Helios Logistics Center | At risk · float -1d | ARCO Construction | 2026-05-25 | Open → |
| Schedule | A5210 · Switchgear energization milestone | K Street Garage Pour | Scheduled · 2026-05-30 | Eaton FSE | 2026-05-30 | Open → |
| Commitment | SC-K042 · Storefront glazing — pending owner exec | K Street Garage Pour | Out for signature | Brookfield K Street LLC | 2026-05-20 | Open → |
| Commitment | PO-H311 · ESFR sprinkler heads (1,420 units) | Helios Logistics Center | Issued · awaiting delivery | FireOps GC | 2026-05-22 | Open → |
| Commitment | SC-K047 · Elevator commissioning add-svc | K Street Garage Pour | Drafted · pending review | ThyssenKrupp | 2026-05-19 | Open → |
| Submittal | 08 41 13.04 · Storefront shop drawings (rev 3) | K Street Garage Pour | Out for review · A/E | Cooper Carry A/E | 2026-05-21 | Open → |
| Submittal | 23 73 13.01 · AHU-2 product data + warranty | Helios Logistics Center | Approved as noted | Trane SE | 2026-05-17 | Open → |
| Drawing | A-301 rev 5 — L4 plan, dimensional cleanup | K Street Garage Pour | Pending review | Stanley Beaman & Sears | 2026-05-22 | Open → |
| Drawing | S-201 rev 3 — Helios tilt panel revisions | Helios Logistics Center | Pending review | Walter P Moore | 2026-05-20 | Open → |
| Safety | Near-miss · ironworker swung pipe at L3 SE corner | K Street Garage Pour | Investigation open | Site safety supervisor | 2026-05-22 | Open → |
| Safety | Recordable · finger laceration, drywall L2 north | K Street Garage Pour | OSHA 300 logged | EHS — Envision | 2026-05-15 | Open → |
| Punch | Ceiling grid alignment — L4 East corridor (8 items) | K Street Garage Pour | Open · 8 items | Drywall sub | 2026-05-21 | Open → |
| Daily log | Daily log 2026-05-22 — K Street crew, weather, notes | K Street Garage Pour | Submitted | Field super (M. Reyes) | 2026-05-22 | Open → |
| Daily log | Daily log 2026-05-22 — Helios crew, weather, notes | Helios Logistics Center | Submitted | Field super (J. Tan) | 2026-05-22 | Open → |